1. Project
a.
Elevated Carport Structures located in both gym lots.
b.
Construction deadline is driven by CA Solar Initiative. Solar project needs to
be operational by 9/31/13.
c.
Project team presented Site Utilization plan and discussed how construction
site will be secured
and
isolated from on campus personnel. See Site Utilization plan for details.
2.
Schedule
a.
Construction begins on 5/6/13‐5/7/13 and is completed on 9/9/13.
b.
Summer school is from 6/17‐7/12.
c. Mobilization will occur on
5/4 (Saturday).
d.
Last day of school is 6/7.
e.
Staff returns on 7/24.
f.
Football begins in late August.
g.
Trenching will occur during June/July when construction will have minimal
impact to campus
staff
and students.
3.
Site Utilization
a.
Construction work hours are from 7:00am‐4:00pm.
b.
12x60 and 12x40 storage containers will be relocated along fence outside of
parking lot.
c.
Trenches will be be covered if faculty or students need access in those
designated areas.
d.
School will close out student parking as needed during construction.
e.
Team will work to minimize parking space impacts.
f.
During the start of construction, onsite personnel is to check in at the front
desk until
construction site has been
established and secured.
.